b.) Is the periodic task set a harmonic task set?
c.) What is the hyperperiod of this system?
d.) Create a frame-based static cyclic schedule for these tasks. Take care that it satisfies
all the following constraints:
• the execution of each job fits within a single frame
• the frame of a job begins no earlier than the job's release time
• the frame of a job ends no later than the job's deadline
If you have many possible frames, choose the largest one. Present your schedule in the
form of a Gantt chart.
e.) What is the worst-case response time of each task in your schedule above?
f.) If the execution time of TB changes to 4, create a cyclic schedule for the task set or