Search for question
Question

Consider the network diagram and the five paths: 1. Start -> A > B -> C-> End (duration: 31 days.} 2. Start ->D-> E->F-> End {duration: 18 days.} 3. Start ->

D-> B -> C-> End {duration: 26 days.} 4. Start -> G->H -> -> End (duration: 13 days.} 5. Start -> G-> E->F-> End (duration: 16 days.) If activity D is delayed 6 and activity F is delayed 3 days, will the duration of the project change? O Yes, the project will be delayed O Yes, the project will be ahead of schedule O No, it will be the same

Fig: 1