Question
Consider the network diagram and the five paths: 1. Start -> A-> B> C-> End {duration: 31 days.) 2. Start ->D-> E->F-> End (duration: 18 days.} 3. Start -> D-> B-> C-> End (duration: 26 days.} 4. Start -> G->H-> -> End [duration: 13 days.} 5. Start -> G-> E->F-> End (duration: 16 days.) What is the duration of the proj