Question

D Question 4 1.5 pts Consider the network diagram and the five paths: 1. Start -> A > B -> C-> End {duration: 31 days.} 2. Start ->D-> E->F-> End {duration:

18 days.} 3. Start -> D-> B-> C-> End (duration: 26 days.} 4. Start -> G->H->-> End (duration: 13 days.} 5. Start -> G-> E->F-> End {duration: 16 days.} If activity A is delayed 3 days, will the duration of the project change? Yes, the project will be ahead of schedule Yes, the project will be delayed No, it will be the same

Fig: 1