Question 37562

posted 1 years ago

If activity "100% CD Complete" is delayed by 6 days, will it delay thetotal duration of the project? If yes, then by how many days and why?(10 Points)

View answer

Question 37561

posted 1 years ago

8. What are the IPAS (Immediate Predecessor Activities) of the activity"Receive Permit?" Write down the names and IDs of the activities. (10Points)

View answer

Question 37558

posted 1 years ago

What is the total duration of the activities without using Precedence Diagram Method (PDM) method in this project? Also determine what isthe total duration of the project after the PDM was used to determine the critical paths of the project? (10 Points)

View answer

Question 37557

posted 1 years ago

What are the IPAS (Immediate Predecessor Activities) of the activity"Phase 2 - Interior Finishes?" Write down the names and IDs of the activities. (10 Points)

View answer

Question 37554

posted 1 years ago

Write down the names and IDs of the activities which will not be delayed if this project is delayed by 20 days. Write down the reasons why these activities will not be delayed.

View answer

Question 37556

posted 1 years ago

3. What are the successor activities of the activity "Exterior Finishes?"Write down the names and IDs of the activities. (10 Points)2

View answer

Question 37559

posted 1 years ago

6. Write down the start date and end date of the project. What is the total duration of the project after using PDM method? Also write down the Activity IDs, which are non-critical activities in the project (10 Points)

View answer

Question 37555

posted 1 years ago

. Write down the names and IDs of the activities which will not be delayed if this project is delayed by 20 days. Write down the reasons why these activities will not be delayed.

View answer

Question 37560

posted 1 years ago

7. What are the successor activities of the activity “90% CD Review/Owner?" Write down the names and IDs of those activities. (10Points)

View answer

Question 37563

posted 1 years ago

If the activity “70% CD Design" is delayed by 2 days, will it delay the start date of its successor activities? If yes, then write down the name and IDs of the activities whose start dates will be delayed and by how many days? (10 Points)

View answer

Questions not Found

Most popular subject

Thermodynamics

Essay/Summary

Mechanics

Complex Analysis

Engineering Economics

Calculus

Modern Physics

General Chemistry

Strength Of Materials

Fluid Mechanics

x