Question

Identify the approaches for expediting the construction process. * Liquidated Damages in which owner should pay compensation to the GC for each day later than the approved deadline. * Liquidated

Damages in which the owner pay incentives to GC for each day earlier than the approved deadline. * Liquidated Damages in which GC should pay compensation to the Owner for each day later than the approved deadline. * Project Incentives in which the GC pays incentives to the owner for each day earlier than the approved deadline. * Project Incentives in which GC pays compensation to the Owner for each day later than the approved deadline. * Project Incentives in which the owner pays incentives to the GC for each day earlier than the approved deadline.