Question

Problem 4.3 Calculate the following network (early and late dates and total and free floats) and answer the questions that follow. The network has 2 constraints (shown below). Show your calculations on the network and answer the questions provided in the Answer Sheet for this assignment. SESH=18 H 7 B3 В G 3 8 SS3 K 8 FS5 A с FS3 F 7 5 4 FFO L 4 D 4 FS4 EO E SS3 M 9 7 SLFM=20 N 5 P 8

Fig: 1