Question
Q1 Earned Value The following bar chart shows the activities to complete a project in 6 months. The total project cost is $700. After 2 months, Activities A & B are completed along with half of activities C and D.These activities have accumulated a cost of $200. Note : Do not insert ($ or () or (%) sign. However do