1. A 50-Hz system consists of two interconnected areas, as shown in Figure 1. Area 1 has an
electric vehicle (EV) charging station and Area 2 has a wind farm. The parameters for both
areas are given in the table below:
Area
Speed regulation, R
Frequency sensitive load, D
Frequency Bias constant, B
Base power
Area 1
EV charging
station
APtie1
1
2
R₁ = 0.04 pu| R2 = 0.05 pu
D₁ = 2 pu
D₂ = 1 pu
B₁ = 3 pu
B₂ = 5 pu
100 MVA
100 MVA
APtie2
Area 2
FŰ
Wind farm
Figure 1
Initially, the generators in both areas are operating in parallel at the nominal
frequency and the tie-line is unloaded when the EV charging power suddenly
increases by 90 MW and the wind farm power suddenly increases by 30 MW
simultaneously. (Hint: assume wind farm power as a negative load change.)
(a) Calculate the new steady-state system frequency in Hz.
[2 marks]
(b) Calculate the change in mechanical power and change in frequency-sensitive
load in each area. Express your answers in per-unit.
[2 marks]
(c) Calculate APtie1 and APtie2 by forming power balance equation in each area.
Hence, or otherwise, determine the area control error (ACE) for each area.
Express your answers in per-unit.
[4 Marks]
(d) Explain how load frequency control (LFC) can eliminate the tie-line error and
area control error for each area in part (c). [No calculations needed]
[2 marks]
Fig: 1