Question

Question 8.

Which of these monitoring and controlling activities is NOT appropriate for this project?

A. Using a fishbone diagram to determine the root cause of the problem

B. Relying on a Gantt Chart to keep the project team on schedule

C. Following the communications management plan to keep hospital and school stakeholders

informed of fundraising progress

D. Updating the truck rental company providing the parade float trailer

E. Updating the Beckley Elementary PTA president about silent auction items