Question

Set up AON network (25 points), find the project duration (15 points), calculate Total Slack and Free Slack for each activity (25 points), and identify the critical path (10 points).

Show all your calculations.Draw the equivalent AOA network (25 points) of the given project schedule. For calculations you can either type in your answer or include it in the attachment with the schedule network picture or scanned PDF file/s. You can upload maximum 2 files.

Fig: 1

Fig: 2