the demand for the next four months is 850, 1,260, 510, and 980, expressed in thousands of cookies. During a 46-day Period when there were 120 workers, the company produced 1.8 million cookies.Assume that the number of workdays over the four months are respectively 26, 24, 20, and 22. There are currently 100 workers employed, and there is no starting inventory of cookies. a) What is the minimum constant workforce required to meet demand over the next four months? b) Assume that C,= $100 per thousand cookies per month,CH =$100, and C = $200. Evaluate the cost of the plan derived in part (a). c) Formulate as a linear program. Be sure to define all variables and include the required constraints. d) Solve for the optimal solution.