month preconstruction phase. Assume the contractor charges an hourly rate that has a
2.0 multiplier (billing rate of 2.0 times the actual hourly rate to cover corporate costs).
Assume the following team members and durations:
• Project Manager:
Chief Estimator:
.
Chief Scheduler:
• OIC:
.
Superintendent:
• Project Engineer:
.
Company Labor Rates:
.
.
1 day per week
8 hours (assume 120% wage of project manager)
8 hours (assume 80% wage of project manager)
No cost
12 hours
2 hours per week
Project Manager $25 per hour
Superintendent-$30 per hour
Project Engineer-$20 per hour
2. Draft a lump-sum preconstruction services contract for the amount indicated in exer-
cise 1.
3. Draft a time-and-materials preconstruction services contract for exercise 1.
4. Prepare a letter addressed to the Training Center offering to perform preconstruction
services for their project. Explain the advantages of employing a construction team
member during the schematic design phase. Explain why your firm is the best to per-
form this task. Explain to the owner why your choice of fee approach is the most ap-
propriate for this relationship and their project.
Fig: 1