project lifespan of 20 years. At the end of the tenth year, the project must be resurfacedat a cost of $300,000. (a) Calculate the present worth of costs for this project over a 20-year period if the annual interest rate is 5 percent. (b) Convert the value obtained in (a) to equivalent uniform annual costs.