two routes connecting the pair have performance functions t₁ = 2 + 3 (x₁/c₁) and t₂ = 4 + 2
(x2/c₂), where the t's are travel times in minutes, the x's are the peak-hour traffic volumes
expressed in thousands, and the c's are the peak-hour route capacities expressed in thousands
of vehicles per hour. Initially, the capacities of routes 1 and 2 are 2,500 and 4,000 xeh/h.
respectively. A reconstruction project reduces capacity on route 2 to 2,000 yeh/h.
Assuming user equilibrium before and during reconstruction, what reduction in total peak-hour
origin-destination traffic flow is needed to ensure that total travel times (summation of all
Xata, where a denotes route) during reconstruction are equal to those before reconstruction?