(40 Points)The quality firm mentioned earlier, are having another project that is facing a problemto meet the deadline, the information provided below will help in crashing the project to meet

thedeadline. Total Project Indirect cost = 500$.Indirect Reduction in Cost/day= 60$ I.What is the total project cost (10 Points)? I.What is the slope value and max crash for the Improvement task (10 Points)? III.What is the recommended task to crash first in this project (10 Points)? IV.What is the new total project cost after the firs crash iteration (10 Points)?