5 determine the quantity in units of tons of base course hot mix aspha
Question
5. Determine the quantity (in units of tons) of Base Course, Hot mix
asphalt (HMA) and Prime Coat needed to pave a 1,200' by 1,200'
parking lot. The Base Course must be 6" thick, the layers of HMA must
be 0.25" thick (combined total) and 0.15 gallons of Prime Coat can
cover 1 square yard. The density of the Base Course is 2.1 tons per
cubic yard (2.1 T/CY). The density of the HMA is 2.0 tons per cubic
yard (2.0 T/CY). The density of the Prime Coat is 8.1 pounds per gallon
(8.1 lbs/GAL).