activity f is targeted to start 2 days after its earliest start date p
Question
Plot the project S-curve showing the Early Schedule, Late Schedule, and Target Schedule.(Hint: use of Excel is recommended for plotting these curves). In order to create the Target Schedule, assume the following: Activity D is targeted to start 2 days after its earliest start date Activity F is targeted to start 2 days after its earliest start date All other activities are scheduled to start at their earliest possible dates