an activity a and activity b both must start at the same time what is
Question
An Activity A and Activity B both must start at the same time. What is the precedence relationship between them? *SS O (Start to Start with a zero-day lag) *FS O (Finish to Start with a zero-day lag) *SF O (Start to Finish with a zero-day lag) *None of the above