II. The environmental effects should be ignored since the mine e legal thout mitigation
III. The environmental effects should be treated as a sunk cost and therefore ignored
IV. The environmental effects if not mitigated would result in additional cash flows. Therefore, since the mine is legal without mitigation, there are no benefits to performing a "ne
mitigation analysis.
V. The environmental affects should be treated as a remote possibility and should only be considered at the time in which they actually occur
c. Should this project be undertaken?
Galed
Gebed
1. The environmental affects if not mitigated could rest in additional loss of cash flows and/or fines and penalties due to ill will among customers, community, etc. Therefore,
even though the mine is legal without mitigation, the company needs to make sure that they have soticipated all costs in the "no mitigation analysis from not doing the
environmental mitigation.
The project should not be undertaken under the
The project should be undertakan only under the
The project should not be undertaken ander the "mitigate
Even when mitigation is considered the project has a
Even when mitigation is considered the project
mitigation assumption
man
would not mitigate for the environmental impact of the project since its IRR without mitigation is
any would mitigate for the environmental impact of the project since its NPV with mitigation is greater
III. Under the assumption that all costs have been considered, the company would not mitigate for the environmental impact of the project since its NPV without mitigation is
greater than its NPV when mitigation costs are included in the analys
-Select
should be unde
1. Under the assumption that all costs
onsidered, the
than its NPV when mitigation costs are not included in the analysis
Search this cour
IV. Under the assumption that all costs have been considered, the company would mitigate for the environmental impact of the project since its IRR with mitigation is greater
than its IRR when mitigation costs are not included in the analysis
V. Under the assumption that all costs have been considered, the company would not mitigate for the environmental impact of the project since its NPV with mitigation is greater
than its NPV when mitigation costs are not included in the analys
Grade it Now
Save & Continue
Continue without saving
Fig: 1