Search for question
Question

Cost Analysis - 0401-533

Assignment 2: Cost Estimating, Uncertainty Analysis and Cost Planning

Course:

Question 1:

1) Perform quantity takeoff for the foundation structure provided in the

following figure and estimate the quantities of:

1. Excavation

2. Concrete including the concrete slab

3. Gravel

2) Design crew for excavation (labors, excavators, hauling trucks... etc.)

to excavate the above quantity and to haul it to a dumping location 15

km far from the construction site. Estimate productivity of crew and

cost of the excavation process

3) Evaluate uncertainty in the excavation productivity and estimate its

impact on schedule and budget.

Note: Include a list of all assumptions that you have made at the beginning

of the analysis including any missing data in the drawing 45°

3' 0"

1' 0" typical

32' 0"

Plan view

Width 32' 0"

रहे

Length 85' 0"

4" concrete slab

4" gravel

Typical section view

85' 0"

3' 0"

10' 0"

1'0"

3' 0" 3' 0"

45° Question 2:

Given the bridge abutment shown below, estimate its construction cost.

Data for this problem should be extracted from both: 1) UAE construction

data and 2) Published data such as the RS Means Unit Price Estimating

Methods (available in the University library).

1) Perform quantity takeoff of the formwork and concrete needed to

build the abutment

2) Design minimum reinforcing steel mesh for the abutment (provide the

reinforcing steel drawings) and do quantity takeoff of steel (Select

appropriate design loads and specifications of the material)

3) Use resource numeration to design crews (labour and power tools) to

build the formwork, to place concrete and to fix the reinforcing steel.

4) Specify productivity of the different crews

5) Estimate cost of the materials

6) Estimate cost per unit of work (i.e. cost per ton of fixing steel, cost per

m³ of placing concrete... etc.

7) Study the market trends in term of adding overhead, contingency and

profit and prepare a bid proposal to build the abutment package.

30'

50'

1'

30'

8′