Create a bar chart showing the typical project sequencing of the following activities. a. List all the activities in their proper order. b. Include programming, schematic, design development and construction

plans for each design activity. (Only architectural will have programming). c. For the bar chart use the durations (x) behind each activity. (All durations are in months). Electrical Engineering (5) Landscaping Design (5) Structural Design (6) Construction (No Duration) Permitting (7 months of 3 rounds of comments) Civil Engineering (6) Architectural Design (10) Mechanical & Plumbing Design (5) 2. Use an Excel format for the bar chart. List the activities on the horizontal and break each vertical column into a month. Then total the schedule in months.