EVM exercise 2

In the following schedule, supposing the actual cost for the end of June and July are

respectively 50 and 60 units and activity % completion is reported as in the table below, what is

the progress trend of the entire project both in terms of cost and schedule from May to June

and then July? Please calculate project CV, SV, CPI & SPI and draw the Excel progress trend over

the three months of May, June & July. Analyze the trend.

Part B) Based on the July progress, when is the project likely to finish? Calculate EAC (t) and ETC(t)(3)

How much is it likely to cost at the end? Calculate EAC & ETC. Analyze the results in details. Use

three calculations of optimistic, pessimistic & most likely as per lecture notes and class exercises.