used for the project; and (iii) why the delivery method should be usedfor the project. Provide your answer with respect to the owner's perspective. (30 points) a. A company which owns many supermarket stores (e.g., Walmart), wants to build anew store. The store will be similar in size and design to other stores owned by the company. b. A hospital owner needs to build a multi-story addition onto the hospital building to add new diagnostic equipment, surgery rooms, and labs. Ongoing hospital operations must continue during construction. c. A small city wants to build new restroom facilities and a parking lot in a city park.
Fig: 1
Fig: 2
Fig: 3
Fig: 4