Question

For the following set of tasks:a.) What is the total processor utilization of this system?b.) Is the periodic task set a harmonic task set?c.) What is the hyperperiod of this system?d.) Create a frame-based static cyclic schedule for these tasks. Take care that it satisfies all the following constraints:- the execution of each job fits Within a single frame- the frame of a job begins no earlier than the job's release time- the fame of a job ends no later than the job's deadline If you have many possible frames,choose the largest one. Present your schedule in the form of a Gantt chart.e.) What is the worst-case response time of each task in your schedule above?f.) If the execution time of Tb changes to 4, create a cyclic schedule for the task set or argue that a valid schedule does not exist.