Now, assume that you have worked 10 days. During

Question
Now, assume that you have worked 10 days. During this time, a total of $18,000 has been billed to the owner (yet $20,000 in costs have been incurred). Determine the

following: - ВCWS • CV Is the project over, under, or on budget? Is the project ahead of, behind, cor on schedule?EAC • EAC