Problem 2 (10 Points) Use the building layout provided. Determine the roof dead load and also the roof live load (in psf) to be applied to Column B2. The roof

of the building is flat. It is composed of 3-ply ready roofing on 3 inches of reinforced concrete.The ceiling beneath the roof is a suspended ceiling.