10
±
A new contract was written with Company A with the following stipulations:
Cpk =
1.4, Specification Nominal (N) =
The Supplier found that their process average of
by as much as
10 could vary
0.2 mils.
The Supplier decided to monitor quality
with a P-Chart (n =
50). Find the following:
0:
Pbar:
UCLp:
Reject Rate (RR):
PPM
LCLp:
NOTE: P-Chart Calculations are separate from the Cpk calculations. The
o is derived from the Cpk minimum.
0.5 mils.
Fig: 1