factory building is rented for $1800 per month and the material cost is $50 per unit. The
labor cost is $10/hour. An 75% learning curve applies to labor, and it takes 10 hours to
complete the first unit. The company decides to use the time of the 15th unit as a standard
for cost estimation. If the selling price per unit is P = $600 -0.04D, find the following:
a. [5 marks] The value of the variable cost per unit c, (round the final answer for c
to the nearest integer).
b. [5 marks] The optimum number of units, to be produced in a month, to maximize
revenue./nC. [5 marks] The optimum number of units, to be produced in a month, to maximize
profit.