Draw the activity-on-node (AON) network diagrams for the following project:


3-10. A 24,000-square-foot warehouse constructed for S1,200,000. If the cost-capacity factor is 0.88, what is the estimated cost to construct a32,000-square-foot warehouse? (


For each of the following predecessor tables: Draw a corresponding AON network. Compute ESt and EFT for each activity.