Question

System B has exactly the same parameters as System A. It also has three 40-MW generators, and the MTTFS of the generators are the same as the ones listed in

Question 1. The load of System Bin a lead time of 2 hours is also 80 Mw .If System A and System B are interconnected, what is the unit commitment risk for system A in the lead time of 2 hours? Assuming the tie line is 100% reliable and has no capacity limit.

Fig: 1