You are in charge of managing a project with six activities. Based on the order of implementingthese activities you developed the following project network: (25 points)
(a) Find the estimate of the mean and variance of the duration of each activity. (b) Find the critical path. (c) Find the approximate probability that the project will be complete within 57 days.