Reinforced Cement Concrete

Search for question

Questions & Answers

2. Give the abbreviations for the following terms: a. acoustical tile ceiling b. asbestos board c. concrete masonry unit d. manufacturer e. on center_ f. pounds per square inch g. American Wire Gauge h. galvanized i. equal j. schedule


For each statement, specify whether it is true or false regarding positions that make up the members of the on-site construction management team. 1. Superintendent 2. Carpenter 3. Owner 4. Assistant superintendent 5. Field engineer 6. Structural engineer


For each statement, specify whether it is true or false regarding the construction stages. 1. During the construction stage,there is a pre-construction meeting for all subcontractors and major material suppliers to set the tone and establishes the ground rules for the job. 2. During the construction stage,value engineering is preformed to analyze the design, products, and materials associated with the project to determine whether the plans, specs, or overall design are accurate. 3. Mobilization during construction stage includes activities such as setting up field office, temporary storage facilities, securing the site and establishing job site management systems. 4. During the construction stage,coordination of all trades must be proactively managed for the job to run smoothly. 5. During the construction stage,schematic or conceptual design helps the contractors to estimate the project costs. 6. Programming is typically done during the construction stage and engages the owners and end users to clarify needs, goals, and objectives for the facility.


1-33 A student accepts a full-time job in November, but a better job comes before graduation in May. What are the ethical dimensions of the student's decision? Would you take the better job? Why or why not?


A..........is used to manage all of the loose ends, minor repairs,adjustments, and missing items at the end of the project. *punch list *RFI *change order *statement of proposal *certificate of substantial completion


4.17. Determine the required area of reinforcement and the corresponding reinforcement ratio for the section in Fig P4. 1a if the ultimate moment is(a) 10,000 in-kips and (b) 5000 in-kips. fy = 60,000 psi.


4. Re-solve problem #1 using a yield strength of 60 ksi and a cantilever boundary condition


The official end of the project occurs when the architect releases a *certificate of substantial completion *RFI *change order statement of proposal *bid bond


1. (5 points) Compute oMn for the T-beam shown below. Also determine the value for Asmin. f'c = 4500 psi and fy =60 ksi.


7. Explain why the minimum reinforcement for flexure and shear is required for RC structures.


No Question Found forReinforced Cement Concrete

we will make sure available to you as soon as possible.