Search for question
Question

(20 Points) Answer the following question with (True) if the statement is correct and with(False) if the statement is wrong (4 Points Each) Note: If the answer is wrong with

false answer, write the correct answer with justification. 1. Project is a temporary endeavor undertaken to create a unique product only (_) 2. Time, budget, resources and customer specifications are the project limitations(_) 3. Adding working shifts to a late project will help crashing the project towards thedeadline(_) 4. Finish-to-start (FS) is a logical relationship in which a predecessor activity cannot startuntil a successor activity has finished. (_) 5. The project customer/user not considered as aproject stakeholder. (_)

Fig: 1

Fig: 2

Fig: 3

Fig: 4

Fig: 5

Fig: 6

Fig: 7