Question

1. Resource Allocation. Given the schedule below with the limit of 5 resources (R), perform the following: a. Complete the precedence diagram and indicate the project's duration (number of workdays) without the resource limit. b. Calculate the dates of each activity and the daily resource usage with the resource limit by completing the chart on the next page, or you may use Excel if you prefer. c. Indicate the project's new duration (number of work days) with the resource limit. Activity Predecessor Duration ABCDEFGHIK 1 Resource (R) 0 A 2 A 2 A 1 A 3 B, C, D 1 E 7 Н F 2 H 1 G, J 3 123315112

Fig: 1