Question

2. (5 points) A general contractor entered into a renovation contract with Google. The

contract specifically states that the 'contractor shall absorb all schedule delays due to

Google shutdowns or corporate functions.' Specific events were not addressed before the

contract was signed. The schedule for the project was six months. One month into the

project, a four-week "Google corporate retreat" was held and all contractors were barred

from accessing the site. Is this a valid contract and is the GC required to finish on

time?