Search for question
Question

2. A concrete sewer to be constructed on a 0.1% slope must carry a peak flow rate of 10 cfs and a minimum flow rate of 3 cfs. a) State

assumptions and specify an appropriate pipe diameter b) Calculate pipe velocity at both peak flow and minimum flow c) State why velocity at minimum flow is or is not acceptable

Fig: 1

Fig: 2

Fig: 3

Fig: 4