Question

2.

Refer to Table 1. This table shows estimates of optimistic, likely and pessimistic

durations for activities to be carried out in one of the work packages for the mountain

bike races.

Table 1 - Estimated activity times for works to be completed by company

Activity

Optimistic

Likely

duration

duration

(weeks)

(weeks)

(a)

(b)

(c)

A-B

B-C

B-D

B-E

C-G

D-F

D-G

E-F

F-G

G-H

H-I

H-J

I-K

J-K

2

4

3

2

3

4

1

6

3

2

1

3

5

1

3

6

4

3

5

8

2

7

5

4

3

6

6

3

Pessimistic

duration

(weeks)

5

8

5

4

7

12

3

8

7

6

5

7

7

5

Produce a network showing the activity mean durations, mean earliest start

and latest finish for each activity, the critical path and the estimated overall

mean duration for the work package.

(10 marks)

Calculate the probability of the work package being completed within 30

weeks.

(5 marks)

Differentiate between logic-driven and resource-driven work logic flow

scheduling and discuss the approach most likely to be adopted by PME in

planning the work elements. Support your answer with appropriate examples

in the context of the case study.

Question image 1