Question

2. Resource Leveling. Level the resources for the following schedule. Draw two manpower curves for the project: one before and one after leveling. Indicate the peak number of workers in both cases. Use the early start dates for the "before leveling" schedule. (It is suggested you use Excel to solve this problem). Activity Duration Workers 5 1826260928220064 535223022372573 Predecessor A B A A D A E C F E G MOHLIKENN J Milestone B, C, D, E, F Milestone Н Milestone Milestone Milestone Milestone A A G,H,I,J,K,L,M