Question

2)The team members of Argo consultants have developed the following schedule of activities for their

upcoming project, using their best estimate of completion times.

Draw the project network.

•

Can they complete the project in 70 days? What is the project completion time?

• Show Forward pass and Backward pass. Give the Critical Path.

You can use the space below or upload the network.

Activity

A. Find Location

B. Write Venue

C. Obtain approval from the

professor

D. Complete event planning

E. Do industry background

research

F. Write the final paper

G. Write an oral report

Time (days)

8

4

6

20

16

12

10

Immediate Predecessor

A

B

с

---

D, E

D, E

Question image 1