4) (10 Points) Create a Network Diagram (Activity on Node) schedule using the following -

Duration (Days)

4

Activity

A

B

C

D

E

F

G

H

I

3

4

2

4

2

4

1

6

Predecessor

A

A

B, C

C

D

D, E

E

F, G, H

Fig: 1