Question

4. The building has a zone that has a total cooling load of

300,000 Btu/hr with a sensible load ratio of 0.75. The zone set

point is 77 F. The supply air is at 55 F and 90% relative

humidity. Determine the required supply air volume flow rate

and the zone relative humidity. (20)

Question image 1