Question

5. (15 Points) QUANTITY TAKEOFF (not a full cost estimate) - You are building twenty-two

(22) of the 2'-0"x 2'-0"x 0'- 10"h spread footings shown below. Using the material

schedule at the bottom of the page, estimate the material quantities listed below. Show all

calculations and list all assumptions in the space provided. Don't forget to include waste.

2"-3"

2'-6"

2 x 12 Concrete Form

Plan View

(2) #4 rebar each way

top and bottom

Section A-A

Concrete

2 x 4 Stakes

1'-6"

|||

2-6

2"-3"

2 x 12 Concrete Form

2x4 Stakes

Question image 1