Question

6-10. Figure 6.39 gives the mileage of the feasible links connecting nine offshore natural gas wellheads with an inshore delivery

point. Because wellhead 1 is the closest to shore, it is equipped with sufficient pumping and storage capacity to pump the

output of the remaining eight wells to the delivery point. Determine the minimum pipeline network that links the wellheads

to the delivery point.