Question

Big Dan's Machine Shop is considering the use of a priority scheduling rule in the fabrication shop and

must decide whether to use: (1) critical ratio (CR), (2) earliest due date (EDD), (3) shortest operation next

(SON), or (4) order slack. The current shop status of the company is given here:

Order Number

1

2

3

4

5

Total Remaining

Manufacturing Time

18

12

10

15

20

Time Remaining

until Due Date

12

15

14

18

15

Current Operation

Processing Time

8

5

6

7

6

a. Using the four sequencing rules, compute the scheduling priority for each order given in the table above.

b. What order should be run first under each of these scheduling rules?

Question image 1