It assumes that there is concrete formwork of 1,500 ft². The productivity rate of each worker is 5 ft²/hr. When the crew size is four, estimate the duration in days to complete the work by the determined crew size. Be sure that a partial day (i.e., less than 8 hours)should be counted as one day. (Note: 1 day = 8 hours)