Question

M10.1 A farm owner is going to erect a maintenance building with a connecting electrical generator and

water tank. The activities, activity descriptions, and estimated durations are given in the following table.

Develop a project network for this problem and answer the following questions:

a) Activity A: What is the EFT?

b) Activity E: What is the LFT?

c) Activity H: What is the LST?

d) Activity F: What is the LST?

e) Activity K: What is the EFT?

Activity J: What is the EFT?

f)

g) What activities are on the critical path?

h)

How many days will it take to complete the project?

i) How many days of slack does Activity H have?

j)

How many days of slack does Activity K have?

Question image 1