n mm mpa a 4742 14 material pg m control mik 14 28 days 2x 9 cabes san
Search for question
Question
N/mm²= Mpa
A
4742
14
Material pg/m³) Control Mik
14
28 (Days)
2X
9 Cabes
Sand Col4mm)
3990
9.59 33.73
9 Cyli
9 Pi
Gel (4/6)
878
846
29,91
Cement CEM] 52.58 380
Water
152
3.66 12,9530% 0145L +0.45
1-4605L = 165 L+10%
=236L
GCA
518+10%=2,6L
=6₁73...+10%
± 7.48.88/n SCHOOL OF ENGINEERING
Year 1 Laboratories
CM + CT
(over 2 successive weeks)
Concrete Making + Concrete Testing
MATS105: Introduction to Engineering Materials
Lecturer
Prof. Maulik Patel
Demonstrator Names
Joao Medeiros and Armin Majidian
Demonstrator Email
J.Medeiros@liverpool.ac.uk and A.Majidian@liverpool.ac.uk Health and Safety ЗЗИ БИЗ ПО ЦООНОГ
Lab coats must be worn at all times during the experiment and instructions by lab demonstrators
should be followed exactly and information regarding the labs fire instructions made known. If
the lab requires steel capped boots then they must be worn or admittance into the lab cannot
be guaranteed.
You are reminded that you are required by law to comply with the School's basic rules of lab
safety, as outlined at the start of the first
year.
(2xlesw svizze
ΜΟ
Aims of the Lab (over 2 successive weeks) Mo
1st Week-CM (Concrete Making)
1. To understand mix design for preparing materials and quantities required for making concrete.
2. To carry out a number of practical steps-(weighing, measuring and mixing materials; preparing
moulds for samples; checking concrete workability; casting the concrete into moulds; vibrating the
moulds to remove air pockets)- and to record group inputs of all tasks and procedures.
3. To leave the concrete mould samples to air-cure for 24 hours minimum. (Laboratory technicians
will place the moulds into water tanks for curing on behalf of groups).
4. To return to the same laboratory 7 days later to complete the experimental procedure involving:
(a) removing group samples from the water tank; (b) demoulding each sample using pressurised
air; (c) cleaning and drying the samples; (d) testing each sample to industry standards- the 3 cubes
tested in the compressive machine; and the mini-beam tested in the flexural machine.
5. To record all values obtained from testing, as well as to complete the questions at the end.
2nd Week-CT (Concrete Testing)
The concrete samples will be tested at 7 days. You will test: 3 cubes + 1 mini-beam
The aim of this lab is to:
Remove the concrete samples to be tested from the curing tank
• Transfer the samples to the Structures Lab
• Test the samples
.
Tidy the area for the next group
ML
You will also have a theoretical mix design to complete as a group whilst you wait for your turn to
test.
2 1st Week - CM (Concrete Making)
1
Mix Design
Mix design is carried out in accordance with "Design of Normal Concrete Mixes" (BRE, 1997)
The criteria of the mix are as follows:
•
•
Volume is 0.008 m³ (3 cubes @ 100x100x100, 1 mini beam)
Characteristic compressive strength, 40 N/(mm^2) at 28 days
with a 2.5% defective rate (k = 1.96)
Portland cement class 42.5 (Note we are actually using CEM II/A-L 32.5R)
Bius Circle
Mastercreta
Cement
0049 612 6222
MORTAR Es
=
CE
CONCITY WILLS
TARMAC
Figure 1: Actual Cement Class used in the lab
•
Slump required, 30-60 mm
.
Maximum aggregate size, 20 mm
.
Coarse aggregate, uncrushed (10mm, 20mm)
.
Fine aggregate, uncrushed (70% pass 600 microns)
.
Maximum free-water/cement ratio, 0.55
.
Minimum cement content, 290 kg/m³
Stage Item
Reference
Values
or
1
1.1
Characteristic strength
calculation
Specified
1.2
Standard deviation
Fig 3
3
40 N/mm² 28 days
on defectiv 2.5 %
Propc r no data 8 /mm 2
N/m o 1.3
333
Margin
C1 or
(k=1.96) 1.96 x8 =
(gails Specified on M
16 N/mm²
30N/mm²
1.4
Target mean strength
C2
40+16=56 N/mm²
1.5
Cement strength class
Specified
42.5/52.5 (Actually using CEM II/A-L 32.5R)
1.6
Aggregate type: coarse
Aggregate type fine:
Crushed/uncrushed
Grushed/uncrushed
1.7
47
Free-water/cement ratio
Table 2, Fig 4 0.41
}Use
Use the lower value 0.41
1.8
Maximum free-water/cement ratio
Specified
0.55
22.1
Slump or Vebe time
Specified
Slump 30
-60 mm or Vebe time
S
2.2
Maximum aggregate size
2.3
Specified
Table 3
20 mm
180 kg/m³
Free-water content
3
3.1
Cement content
C3
180+0.41-440 kg/m³
3.2
Maximum cement content
Specified
kg/m³
3.3
Minimum cement content
Specified
290 kg/m³
use 3.1 if s
3.2 use 3.3 if
>3.1
440 kg/m³
3.4
Modified free-water/cement
ratio
4
4.1
Relative density of aggregate
(SSD)
2.6 known/assumed
4.2
Concrete density
4.3
Fig 5
C4
Total aggregate content
2385 kg/m³
40 8=>
765 kg/m³
23 54 1 01
5
5.1
Grading of fine aggregate
Percentage passing 600 μm sieve
70%
5.2
Proportion of fine aggregate
Fig 6
27%
5.3
Fine aggregate content
5.4
} CS
{
1765x0.27=475 kg/m³
1765-475-1290 kg/m³
Coarse aggregate content
Cement
Water
Fine
aggregate
Coarse aggregate (kg) Quantities
(kg)
(kg or litres)
(kg)
10 mm
20 mm
40 mm
per m³ (to nearest 5 kg)
440
180
475
130
860
per trial mix of 0.03 m²
26
14
13
Table 1: Concrete mix design form
2
Method of Mixing
2.1
Weigh Mix Components
Each group should take 3 buckets:
•
2 for 20mm aggregate (this is to keep the weight below 20kg) 1
for 10mm aggregate
•
1 for fine aggregate ("sand" is equivalent to "fine" aggregate) □ 1
for cement
1 for water
Cement
20mm agg.
10mm agg
Fine/sand
Figure 2: Aggregate and Cement Containers
Take aggregate and cement from the barrels using the scoops provided and according to the quantities
of your "corrected mix design" (Section Error! Reference source not found.)
Note-do not fill a bucket with more than 20kg-this is important for 20mm aggregate.
5