name ce 444 contracts and specifications exam number 2 worth a total o
Search for question
Question
NAME:
CE 444 Contracts and Specifications
Exam Number 2 (Worth a total of 50 points)
March 2024
You may refer to your notes for this exam. The test is set up as a true/false, multiple choice, short
answer, matching and brief paragraph essay format. This take-home exam is due back on 5 April by
11:59 pm (central time).
TRUE or FALSE (circle correct answer, 1 points/question for total of 5 points)
1. ① or F Technical Specifications describe quality while Contract Drawings describe quantity
2. ⑪ or F The General Requirements are part of the General Conditions of the Contract
3. T or F General Conditions take precedence over Supplemental Conditions
4. T or F When following the rules of contract interpretation, Parol Evidence trumps Extrinsic
Evidence
5. ① or F In Private Contracting, an Owner may be liable to pay a subcontractor even if the
prime contractor was paid in full for the work.
Fill in the Blank / Short Answer / Matching (1 point per blank)
6. Match the following terms with the most correct explanation (4 points)
Term
1 Payment Bond
Explanation
4
Provides the owner with an amount to cover the
damages/costs if the apparent low withdraws
2 Bid Bond
2
Provides the owner with a means for completing the
work if the contractor cannot complete it.
3 Lien
1
Protects suppliers, subcontractors and employees
Non-payment by the General Contractor
4 Performance Bond
Used primarily in private contracting; the General
3
contractor and first-tier subcontractors place a debt
upon the facility if they haven't been paid.
1 7. Identify the method of specifying (ie prescriptive, performance, proprietary closed,
proprietary open, all-inclusive, reference) (6 points):
a. “Plant trees in locations indicated by Contracting Officer.”
Specification Method
performance
b. “Polethylene pipe shall be installed in accordance with ASTM D2774 using
AWWA C150/A21.50 Type 4 laying condition."
Specification Method
reference
c. “Benches will be DuMor Recycled Plastic Bench, Model 16PL or equal.”
Specification Method
propietary open
d. "Seams shall be continuously sewed using a J-type seam with two rows of a 401
interlocking chain stitch.”
Specification Method
Prescriptive
e. "A stand of turf is defined as a uniform stand of grass at least 3 inches tall with a
minimum of 100 grass plants per square foot."
Specification Method_
performance
f. "Install Whipps series 923-C stainless steel slide gate."
Specification Method
propietary Closed
8. We discussed 4 different sources for contract document templates in the United States - in
addition to the Federal Acquisition Regulations. Name the 4 sources. You must list their
names
-
not just their acronyms (4 points):
1) DBIA - Design Build Institute of America
2) EJCDC - Engineers Joint Contract Documents Committee
3) AIA - American Institute of Architects
4) Consensus DOCS
9. AIA and EJCDC both publish standardized contract documents. Name at least 2 document
families from each of them. (4 points)
AIA: ) Design - Build Family
2) International Family
EJCDC: D Engineering (owner-Engineer, Engineer- Subconsultant)
2) Construction (owner-Contractor)
2 10. An estimate includes direct costs, indirect costs, impact and time. For the items listed below,
indicate which category they fall into: (8 points)
A. Carpenter
B. Project Manager
C. Rent for the Company Storage Yard
Direct Costs
Indirect Costs
Indirect Costs
D. Rebar for the Foundation Slab
Direct Costs
E. Propane to Heat the Concrete during Winter Curing Direct Costs
F. OT costs for additional crew due to the change order
G. Excavator
H. 3 additional days in contract time due to the change
Impact and Time
Direct costs
Impact and Time
11. Match the Socio-Economic Program with the Fact:
Program
| 8(a)
2 WOSB
3 HUBZone
4 SDVOSB
Fact
3 Qualified areas based on census data
4 This type of business receives preference on VA contracts
| 9-year program with the SBA advocating for the Small Business
2. Applicable to certain North American Industry Classification
Systems (NAICS) codes
12. Can the Owner stop work? (Yes or No)
13. How many types of Differing Site Conditions are there?
Yes
2
14. Can the Contractor perform work before providing submittals?
NO
15. Name 3 conditions for which a Contractor will be owed additional time to complete
the contract.
1)
Change Orders
Delays by the Owner
3
3) unforseen Site conditions ELEVATION
945
940
930
16. If the Contractor has deficient work, which of these is correct:
The Owner can reject the work and require the Contractor to correct it
B. The Owner can accept the work for consideration (ie, a credit back from the
Contractor)
C. The Owner has no rights. The Contractor did the work and it must be accepted
and paid for.
17. You are required to develop a schedule for a project. Which type of schedule do you
recommend for the following:
A. This is a complex long-term project with multiple submittals, permits and long-
lead items. You have multiple crews and subcontractors.
Type of Schedule:
PERT-CPM
B. This is an underground pipe project – short duration, very linear sequence of work.
Line of Balance
Type of Schedule:
18. Fill in the attached CPM.
EXTRA CREDIT 2 (4 points):
Match the drawing types with the drawing:
Plan
CS504
MATCH
920
EXISTING
910
900
890
880
Profile
12" R20 RIPRAP
6" BEDDING
GEOTEXTILE, TYPE 1
36" R140 RIPRAP
13" BEDDING
GEOTEXTILE, TYPE 1
MATCH STILLING BASIN
Section
Detail
Section
DRY SEED MIX
945
CONTROL LINE "R"
EL, 930.5
940
6
CHANNEL CONTROL LINE C
BENCH SLOPE AND WIDTH
VARY, SEE SHEET CS402
FOR REQUIREMNTS
30'
EL. 929.6
C$504
15
EXISTING GROUND
EL. 919.0
1V7H
EL. 915.5
EMBEDDED LEVEE
EL. 923.5
EXCAVATION
88.25
88.25
17
36" R140 RIPRAP
13" BEDDING
GEOTEXTILE, TYPE 1
54" R470 RIPRAP
18 BEDDING
GEOTEXTILE, TYPE 1:
875
-400
-350
-300
-250
-200
-150
-100
-50
50
100
150
200
STA. C 13+02.43
4
12" R20 RIPRAP
6 BEDDING
GEOTEXTILE, TYPE 1
EL. 916.5
IMPERVIOUS FILL
INSPECTION TRENCH
1V:2H CUT SLOPES.
12 TOPSOIL
930
W920
EXCAVATED MATERIAL BERM
(RANDOM FILL)
910
900
890
880
875
250
300
350
400
500
550
600
650
700
750
-800
ELEVATION EXTEND RIPRAP TO EL. 919.0 RT SIDE
MATCH DITCH-
D10+60
D10-
END CHANNEL
STA.C 10+50.00
STA. DIV 1566+68.10-1
STA. R19 15+73.00
REACH 19 DIVERSION CHANNEL
BY OTHERS
TOP CUT
GENERAL NOTES:
15 MAINTENANCE ROAD
8 AGGREGATE BASE COURSE
GEOTEXTILE TYPE 2
FLOW
BEGIN RIPRAP
STA. C 10+50
05+00
TEMPORARY DITCHING
WORK LIMITS
1V4H
Plan
EMBEDDED LEVEE
00+22 003
15' MAINT, ROAD
-CONTROL UNE R
DETAIL PLAN
CS40 CONTROL BUILDING
DIVERS
CHANNE
14-209M
CS302
CS310
Detail
X-2809592.60
W19-4 1 1/4X3/16
STAIR TREAD
LANDING SIDE
BEAM C6X10.5-
LANDING GRATING
TVSH
14-208M
DO+00
C5303
00+81
15-231M
00+10
O
SITE PLAN L
CONTROL BUILDING
AND PARKING
1V:6H
RT DAM EMBANKMENT TOE
CONNECTING
CHANNEL
41
END R140 RIPRAP
15-233M
STA. C 16+85
DIVERSION INLET STRUCTURE
C00+00
C$306
OTHERS
CHANNEL BY
008
CONTROL LINE "O"
LTEMB
SEDIMENSIONS
MAY!
Y VARY)
Y-404253.55
ABANDONED MIDCONTINENT
COMMUNICATIONS FIBER
SHEAR TAB
SHEAR TAB
LANDING BEAM
C9X13.4
B
LANDING PLATFORM TO
STAIR TO CONCRETE
CONNECTION
ELEVATION VIEW
SCALE: NOT TO SCALE
5
TV4H
1V4H
T
LT DAM EMBANKMENT
15' MAINT. ROAD
BEGIN STA. O 5+00
RT EMB (RANDOM FIL
-CONTROL LINE"T"
VH
T2
1V:7H
CHANNEL
CS402
1V:7H
TOP CUT SLOPE
CONTROL LINE "C"
Ca
ACTIVE MIDCONTINENT
COMMUNICATIONS FIBER
OPTIC LINE
WORK LIMITS
TH AVE S