Data concerning its second processing department for the month of July 2023 is as
follows:
Beginning
Work in
process
Units
started
into
production
Ending
work in
Units
10,000 $
120,000 $
Costs
Direct
Materials
Conversion
28,000 $
440,000 $
35,920
500,000
4,000
process
Beginning work in process was 100% complete with regard to direct materials and 90%
complete with regard to conversion
Ending work in process was 100% complete with regard to direct materials and 40%
complete with regard to conversion
REQUIRED:/nPrompt 6Calculate the total cost of units transferred to the next department
Answer for prompt 6 Calculate the total cost of units transferred to the next
Fig: 1
Fig: 2